pURAC – disassembly of insulators
Customer : PURAC Gorinchem
subject : disassembly and placing in storage of insulators
In order to relocate part of a production process, Purac commissioned the disassembly of the present pipework and disconnection of the four insulators, internal horizontal transportation to underneath the opening for hoisting out, vertical transportation using a 400-tonne crane and placing the parts on a temporary storage site in order to relocate them to a new site.